SZodixStudyAcademic Library
ShelvesOpen access
Study · an open academic library·Metadata from OpenAlex (CC0)·Shelves·OpenAlex metadata, de-duplicated
Multi-objective optimization of discrete time–cost tradeoff problem in project networks using non-dominated sorting genetic algorithm
16 references·3 citing·30 second hop
Multi-objective optimization of discrete time–cost tradeoff problem in project networks using non-dominated sorting genetic algorithm (2016)Multi-objective optimization of discrete …Handbook on Project Management and Scheduling Vol.1 (2015)Handbook on Project Managemen…A multi-objective facility location model with batch arrivals: two parameter-tuned meta-heuristic algorithms (2011)A multi-objective facility lo…Discrete time/cost trade-offs in project scheduling with time-switch constraints (2002)Discrete time/cost trade-offs…A GA-based fuzzy optimal model for construction time–cost trade-off (2001)A GA-based fuzzy optimal mode…Using Machine Learning and GA to Solve Time-Cost Trade-Off Problems (1999)Using Machine Learning and GA…New computational results on the discrete time/cost trade-off problem in project networks (1998)New computational results on …Complexity of the Discrete Time-Cost Tradeoff Problem for Project Networks (1997)Complexity of the Discrete Ti…Optimal procedures for the discrete time/cost trade-off problem in project networks (1996)Optimal procedures for the di…The Analysis of Activity Networks Under Generalized Precedence Relations (GPRs) (1992)The Analysis of Activity Netw…Project Management With Cpm, Pert and Precedence Diagramming (1983)Project Management With Cpm, …A Dynamic Programming Algorithm for Decision CPM Networks (1979)A Dynamic Programming Algorit…A Simple CPM Time-Cost Tradeoff Algorithm (1971)A Simple CPM Time-Cost Tradeo…MONTE CARLO METHODS AND THE PERT PROBLEM (1963)MONTE CARLO METHODS AND THE P…Critical-Path Planning and Scheduling: Mathematical Basis (1961)Critical-Path Planning and Sc…A Network Flow Computation for Project Cost Curves (1961)A Network Flow Computation fo…Critical-path planning and scheduling (1959)Critical-path planning and sc…Integrating environmental sustainability in construction Time-Cost trade-off for decision-making using hybrid NSGA-III and MOPSO approach (2025)Integrating environmental sus…Multi-Objective Optimization in Construction Project Management Based on NSGA-III: Pareto Front Development and Decision-Making (2024)Multi-Objective Optimization …An ex ante control chart for project monitoring using earned duration management observations (2017)An ex ante control chart for …Activity networks: Project planning and control by network models (1977)Activity nets: A guided tour through some recent developments (1995)A branch-and-bound procedure for the resource-constrained project scheduling problem with generalized precedence relations (1998)The multi-mode resource-constrained project scheduling problem with generalized precedence relations (1999)Critical-Path Planning and Scheduling (1959)Time, cost and quality trade-off in project management: a case study (1999)Fuzzy-multi-objective particle swarm optimization for time–cost–quality tradeoff in construction (2010)The discrete time-cost tradeoff problem revisited (1995)The discrete time/cost trade-off problem: extensions and heuristic procedures (2007)Robust scheduling and robustness measures for the discrete time/cost trade-off problem (2010)Discrete time–cost–environment trade-off problem for large-scale construction systems with multiple modes under fuzzy uncertainty and its application to Jinping-II Hydroelectric Project (2012)Application of a Technique for Research and Development Program Evaluation (1959)HEURISTIC ALGORITHMS FOR RESOURCE-CONSTRAINED PROJECT SCHEDULING: A REVIEW AND AN EMPIRICAL ANALYSIS (1989)When neighboring disciplines fail to learn from each other: The case of innovation and project management research (2018)Fuzzy sets (1965)Fuzzy sets (1996)Bid/no-bid decision-making – a fuzzy linguistic approach (2004)Overview of the Application of “Fuzzy Techniques” in Construction Management Research (2009)Six decades of project management research: Thematic trends and future opportunities (2016)An Analytical Study of the PERT Assumptions (1964)Distribution of the Time Through a Directed, Acyclic Network (1965)Bounding the Project Completion Time Distribution in PERT Networks (1985)Markov and Markov-Regenerative pert Networks (1986)An iterative scheduling technique for resource-constrained project scheduling (1992)Simulating Project Work Processes and Organizations: Toward a Micro-Contingency Theory of Organizational Design (1999)Project management with time, cost, and quality considerations (1996)Pluralism in Project Management: Navigating the Crossroads of Specialization and Fragmentation (2010)A hybrid genetic algorithm for the discrete time–cost trade-off problem (2012)Using Genetic Algorithms to Solve Construction Time-Cost Trade-Off Problems (1997)An integrated survey of deterministic project scheduling (2001)
this work references cited by second hop

References

  • 1961Critical-Path Planning and Scheduling: Mathematical Basis902 cited
  • 1959Critical-path planning and scheduling623 cited
  • 1983Project Management With Cpm, Pert and Precedence Diagramming400 cited
  • 1961A Network Flow Computation for Project Cost Curves366 cited
  • 1963MONTE CARLO METHODS AND THE PERT PROBLEM240 cited
  • 1971A Simple CPM Time-Cost Tradeoff Algorithm223 cited
  • 1997Complexity of the Discrete Time-Cost Tradeoff Problem for Project Networks209 cited
  • 2001A GA-based fuzzy optimal model for construction time–cost trade-off182 cited
  • 1996Optimal procedures for the discrete time/cost trade-off problem in project networks157 cited
  • 1992The Analysis of Activity Networks Under Generalized Precedence Relations (GPRs)156 cited
  • 1979A Dynamic Programming Algorithm for Decision CPM Networks117 cited
  • 1999Using Machine Learning and GA to Solve Time-Cost Trade-Off Problems112 cited
  • 1998New computational results on the discrete time/cost trade-off problem in project networks107 cited
  • 2015Handbook on Project Management and Scheduling Vol.1103 cited
  • 2002Discrete time/cost trade-offs in project scheduling with time-switch constraints

Only edges whose both ends are imported exist here. Widen the year window, or show the whole map. Back to the work

68 cited
  • 2011A multi-objective facility location model with batch arrivals: two parameter-tuned meta-heuristic algorithms66 cited
  • Cited by

    • 2024Multi-Objective Optimization in Construction Project Management Based on NSGA-III: Pareto Front Development and Decision-Making42 cited
    • 2025Integrating environmental sustainability in construction Time-Cost trade-off for decision-making using hybrid NSGA-III and MOPSO approach39 cited
    • 2017An ex ante control chart for project monitoring using earned duration management observations12 cited